Detached garage reconstruction after vehicle impact

Multifamily Reconstruction / Structural Repairs / Vehicle Impact Repairs

Location
Los Angeles
Property Type
Condominium
Cause of Loss
Vehicle impact
Project Size
None
Timeline
2 weeks for insurance inspections, estimate for repairs. 1 week demo. 1 week framing. 4 weeks drywall, paint, garage door, exterior stucco and paint.
Before
Detached garage reconstruction after vehicle impact - Before
Detached garage reconstruction after vehicle impact - Before
Detached garage reconstruction after vehicle impact - Before
Completion
Detached garage reconstruction after vehicle impact - Completion
Detached garage reconstruction after vehicle impact - Completion
Detached garage reconstruction after vehicle impact - Completion

The Challenge

The vehicle impact caused damage to multiple building components, including structural framing and exterior finishes. Safety concerns required immediate action to stabilize the affected area and prevent further damage.

Emergency Response

None

Insurance Coordination

Turquoise Construction worked closely with the insurance carrier throughout the reconstruction process. Detailed repair estimates were prepared using industry-standard estimating software and supported by photographs and project documentation. Our team maintained ongoing communication with adjusters, owner, and HOA to facilitate approvals and keep the project progressing toward completion.

Reconstruction Scope

Following completion of inspections and approval of the repair scope, reconstruction activities were initiated to restore the property to pre-loss condition; garage door replacement, exterior wall repairs, structural and framing repairs, exterior finish restoration, and interior repairs which include; insulation, drywall, and paint.

Results

The detached garage was successfully restored and returned to pre-loss condition. Damages were repaired, allowing the owner to continue in a safe, functional, and fully restored environment. Through coordinated planning, insurance collaboration, and quality reconstruction services, the project was completed efficiently while minimizing disruption to tenant and property operations.

Key Takeaways

This project demonstrates the importance of working with an experienced reconstruction contractor capable of managing insurance coordination, communication, scheduling, and restoration activities under a single point of responsibility. By maintaining clear communication with all stakeholders and focusing on efficient project execution, Turquoise Construction successfully restored the property and helped return to normal conditions.